Aluminum wire casting production line operating


Aluminum wire casting production line operating ---Part 2: Operation of aluminum melting furnace

 

(1) Check whether the equipment of aluminum melting furnace is running normally; 

 

(2) Prepare 2T scrap aluminum material; 

 

(3) Before starting the melting furnace, the crucible and tilting device shall be checked to ensure the equipment is in good condition.

 

(4) Feeding in the furnace starts heating. Heating requires low power to heat the crucible to 200 degrees and keep it warm for 20 minutes. After heating to the melting temperature, if the crucible is not used for a long time, the crucible shall be re- baked according to the requirements of the baking curve. 

 

(5) When the temperature of aluminum water in the first furnace reaches 850 degrees, put aluminum water into the holding furnace. 

 

(6) Check whether there are fireballs in the aluminum melting furnace every hour, and deal with them in time.

 

(7) When discharging water from the aluminum melting furnace, observe the water flow of aluminum in the chute in time to prevent blockage and cut-off. 


We use optional cookies to improve your experience on our site, including through social media connections, and to serve personalized ads based on your online activity. If you refuse optional cookies, we will only use cookies that are necessary to provide you with the service.  Privacy Statement

Leave your inquiry now, and get a systematic solution later.

We will contact you within one working day. Please pay attention to your email.

Submit message